How Open Access Renewable Energy Could Change Industrial Power Procurement in Kerala
Back to Insights
Open Access 9 min read1 July 2025

How Open Access Renewable Energy Could Change Industrial Power Procurement in Kerala

Open access lets industries buy renewable power from any generator using the state grid as a delivery network. Here's exactly how it works โ€” and why Kerala industries should understand it now.

Aswanth SR

Aswanth SR

Chief Commercial Officer & Founder

Share:

Open access is one of those regulatory provisions that has been available to Kerala industries for years โ€” but is often only discovered when a consultant or advisor brings it up. That's partly because state utilities don't advertise it, and partly because the terminology feels intimidating.

Let's fix that. Here's open access, explained in the language of someone who runs a factory in Kerala.

The One-Sentence Explanation

Open access means you can buy electricity from any generator in India โ€” including a renewable farm hundreds of kilometres away โ€” and have it delivered to your factory using the existing power grid. You pay the utility for the use of their network. But the total cost is lower than buying everything from them.

Why Does This Matter for Kerala Industries?

Kerala's own renewable generation is constrained by terrain and land availability. But Tamil Nadu, Karnataka, and Andhra Pradesh have abundant wind and solar. Open access allows a factory in Ernakulam or Thrissur to effectively access power from a wind farm in Gadag or a solar park in Tamil Nadu โ€” at a fraction of the KSEB tariff.

  • Kerala HT tariff all-inclusive: โ‚น10โ€“12/unit (typical)
  • Open access renewable all-inclusive (Kerala landing): โ‚น6โ€“8/unit
  • Group captive all-inclusive (captive status): โ‚น4.5โ€“6/unit
  • Difference: 30โ€“50% savings depending on model and state

Key Terms Demystified

  • Wheeling: The fee for using the transmission/distribution network to move power from generator to consumer
  • Banking: Storing surplus generation in the grid and drawing it back later โ€” like a power account
  • Scheduling: Telling the grid operator in advance how much power you expect to draw (and when)
  • Cross-subsidy surcharge (CSS): A levy on consumers who shift away from the utility to open access โ€” varies by state and consumer category
  • Transmission loss: A small percentage of power "lost" in transmission that you compensate for via additional units

Open Access in Kerala: Current Reality

Kerala's open access framework is governed by KSERC regulations. For industrial consumers with 1 MW+ contracted demand, short-term and long-term open access are available. The framework is still maturing compared to Karnataka or Tamil Nadu, but it is legally available and has been used by a growing number of large consumers.

  • Open access eligibility: 1 MW+ contracted demand (state-level)
  • Applicable charges: Wheeling, transmission, scheduling, CSS, deviation settlement
  • Long-term open access: Requires KSEB network capacity assessment
  • Banking provisions: Available under KSERC framework
  • Inter-state open access: Governed by CERC; uses STU and CTU infrastructure

The regulatory landscape for open access in Kerala is evolving. Policy changes โ€” on CSS, banking, and network access โ€” can impact the economics significantly. It's important to work with advisors who track these developments actively.

Open Access vs Group Captive: The Honest Comparison

  • Open access: No equity commitment, easier to set up, but CSS and surcharges reduce savings vs captive
  • Group captive: Lower effective tariff, longer setup, requires equity investment in generating company
  • For most large industries (2 MW+): Group captive delivers better long-term economics
  • For mid-size industries (1โ€“2 MW) or those preferring zero equity: Open access PPA is the cleaner entry point

Understand Open Access Options for Your Kerala Factory

Our team tracks KSERC regulatory developments closely and can walk you through what open access options are currently viable for your facility.

Open Access Kerala Industrial Procurement Wheeling Renewable

Frequently Asked Questions

About the author

Aswanth SR

Aswanth SR

Chief Commercial Officer & Founder